Atlantic Yards Arena & Redevelopment Project
Latest Atlantic Yards News
The plan for the more than $4 billion project includes 16
buildings for residential, office, retail, community
facilities, parking, and possibly hotel uses. These
buildings provide approximately 5,325 to 6,430 housing
units, 2,250 of which will be affordable. The Project also
contains 8 acres of publicly accessible open space, and the
Arena, a venue for the Nets professional basketball team, as
well as one for the City’s colleges and local academic
institutions. The Project is expected to create
thousands of construction and permanent jobs.
Empire State Development, in conjunction with the
Metropolitan Transportation Authority (MTA), the City of New
York, and affiliates of the Forest City Ratner Companies,
proposes to implement the Atlantic Yards Project in two
phases, with the Project elements on Phase I to be completed
by 2012 and the Project elements on Phase II finished by
2019.
2009 Modified
General Project Plan (MGPP) (June 23, 2009)
Updated Project Site Plan (September 2009)
Updated Site Control Map (September 2009)
Blight Study (2006)
Design
Guidelines (2006)