Atlantic Yards Arena and
Redevelopment Project
ATLANTIC YARDS CONSTRUCTION
UPDATE
Weeks beginning September 10, 2007
and
September 17, 2007
In an effort to keep the
Atlantic Yards Community aware of upcoming
construction activities, ESD and Forest City
Ratner are providing the following outline
of anticipated upcoming construction
activities.
Please note: the scope and
nature of activities are subject to change
based upon field conditions.
Long Island Rail Road/Vanderbilt Yard Work
-
Mid-block piles:
Drilling is complete; excavating down a
few feet then installing lagging
-
Excavation of material
and preparation to drill piles at
Southeast Gas Station (block 1121, lot
47)
-
Continue test piles for
Temporary Train Trestle foundation
piles.
-
Continue test pits on
Pacific Street within the area which has
already been closed pursuant to the
Pacific Street Maintenance and
Protection of Traffic Plan (MPT) on
block 1121 to confirm location of
existing street utilities proximate to
layout of piles.
-
Mobilization to East
Portal; preparation for drilling of
piles.
-
Mobilization to drill
foundation piles for cable bridge
(adjacent to 6th Avenue Bridge).
-
Continue soil excavation
and removal in block 1121 west to east.
-
Continue construction
and debris removal.
Abatement and Demolition Work
All work described below
will comply with the additional oversight
and protocols by the Department of Buildings
(DOB) that were established on April 30th.
-
Clean-up and backfill
has been completed at 175 Flatbush
Avenue (block 1118, lot 6), and 177
Flatbush Avenue (block 1118, lot 5).
-
The double-shift
abatement and emergency demolition work
on the parapets has been completed at
800 Pacific Street (block 1129, lot 25);
Completion of the roof abatement is
underway with an anticipated duration of
three-five weeks. Once all of the
abatement is completed, demolition of
the building will commence.
-
Demolition has commenced
at 546 Vanderbilt Avenue (block 1129,
lot 54), and is anticipated to be
underway for the next two–three months.
-
Abatement has been
completed at 814 Pacific Street (block
1129, lot 45), and 542 Vanderbilt Avenue
(block 1129, lot 50). Demolition will
begin within this two-week period;
Abatement has been completed at 818
Pacific Street and will be underway at
538 Vanderbilt (same block and lot,
1129/46).
-
Abatement has been
completed at 465 Dean Street (block
1127/lot 54). Demolition will begin
within this two-week period.
|
|
|
|