Weeks beginning August 27, 2007 and September
3, 2007
In an effort to keep the
Atlantic Yards Community aware of upcoming
construction activities, ESD and Forest City
Ratner are providing the following outline
of anticipated upcoming construction
activities.
Please note: the scope and
nature of activities are subject to change
based upon field conditions.
Long Island Rail Road/Vanderbilt Yard Work
-
Mid-block piles are
complete; excavation and lagging to
begin from mid-block piles south.
-
Excavation of material
and preparation to drill piles at
Southeast Gas Station (block 1121, lot
47)
-
Continue test piles for
Temporary Train Trestle foundation
piles.
-
Continue test pits on
Pacific Street within the area which has
already been closed pursuant to the
Pacific Street Maintenance and
Protection of Traffic Plan (MPT) on
block 1121 to confirm location of
existing street utilities proximate to
layout of piles.
-
Mobilization to East
Portal; preparation for drilling of
piles.
-
Continue soil excavation
and removal in block 1121 west to east.
-
Continue construction
and debris removal.
Abatement and Demolition Work
All work described below
will comply with the additional oversight
and protocols by the Department of Buildings
(DOB) that were established on April 30th.
-
Demolition has been
completed at 175 Flatbush Avenue (block
1118, lot 6), and 177 Flatbush Avenue
(block 1118, lot 5). Cleanup and
backfill will be underway.
-
The double-shift
abatement and emergency demolition work
on the parapets at 800 Pacific Street
(block 1129, lot 25) will be completed,
and then the completion of the roof
abatement will commence with an
anticipated duration of four-six weeks.
Once all of the abatement is completed,
demolition of the building will
commence.
-
Demolition has commenced
at 546 Vanderbilt Avenue (block 1129,
lot 54), and is anticipated to be
underway for the next two–three months.
-
Abatement will continue
at 814 Pacific Street (block 1129, lot
45), 818 Pacific Street (block 1129, lot
46), and 542 Vanderbilt Avenue (block
1129, lot 50).
-
Abatement will continue
at 465 Dean Street (block 1129/lot 54).
|
|
|
|