Atlantic Yards Arena and
Redevelopment Project
ATLANTIC YARDS CONSTRUCTION
UPDATE
Weeks beginning August 13, 2007 and August 20,
2007
In an effort to keep the
Atlantic Yards Community aware of upcoming
construction activities, ESD and Forest City
Ratner are providing the following outline
of anticipated upcoming construction
activities.
Please note: the scope and
nature of activities are subject to change
based upon field conditions.
Long Island Rail Road/Vanderbilt Yard Work
-
Continue drilling
Support of Excavation (SOE) mid-block
piles in block 1121.
-
Mobilize to Southeast
Gas Station (block 1121, lot 47);
Install construction fence on Vanderbilt
Avenue, partial closing of sidewalk will
occur in connection with appropriate DOT
permits. Partial removal of soil.
-
Test pile for Temporary
Train Trestle foundation piles.
-
Test pits on Pacific
Street within the area which has already
been closed pursuant to the Pacific
Street Maintenance and Protection of
Traffic Plan (MPT) on block 1121 to
confirm location of existing street
utilities proximate to layout of piles.
-
Grade South Lead Track
for LIRR access to East Portal.
-
Continue soil excavation
in block 1121 west to east.
-
Continue construction
and debris removal.
Abatement and Demolition Work
All work described below
will comply with the additional oversight
and protocols by the Department of Buildings
(DOB) that were established on April 30th.
-
The double-shift
abatement and emergency demolition work
on the parapets at 800 Pacific Street
(block 1129, lot 25) will continue for
the next three-four weeks. Once this
work is completed, demolition of the
rest of the building will commence.
-
As an extra safety
precaution, the sidewalk bridge at 800
Pacific Street has been extended by 10
feet in front of 603 Dean Street (block
1129, lot 76).
-
Demolition has commenced
at 546 Vanderbilt Avenue (block 1129,
lot 54), and is anticipated to be
underway for the next two months.
-
Demolition is underway
at 175 Flatbush Avenue (block 1118, lot
6), and 177 Flatbush Avenue (block 1118,
lot 5); 177 Flatbush Avenue will likely
be completed within this period.
-
Abatement is underway at
814 Pacific Street (block 1129, lot 45),
818 Pacific Street (block 1129, lot 46),
and 542 Vanderbilt Avenue (block 1129,
lot 50).
-
Abatement will be
underway at 465 Dean Street (block
1129/lot 54).
-
Clean-up of 622 Atlantic
Avenue (block 1119, lot 1) will be
completed.
Utility Work
The sidewalk shed constructed over a transit
manhole in the sidewalk on Flatbush Avenue
between Atlantic Avenue and Pacific Street
will remain in place to prepare the manhole
for cable insulation, abatement and
reconstruction as part of the private
utility/transit relocation work required to
accommodate new sewer infrastructure. This
work will continue through August.
|
|
|
|