Atlantic Yards Arena and
Redevelopment Project
ATLANTIC YARDS CONSTRUCTION
UPDATE
Weeks beginning July 30, 2007 and August 6,
2007
In an effort to keep the Atlantic Yards
Community aware of upcoming construction
activities, ESD and Forest City Ratner are
providing the following outline of
anticipated upcoming construction
activities.
Please note: the scope and nature of
activities are subject to change based upon
field conditions.
Long Island Rail Road/Vanderbilt Yard Work
-
Continue drilling
Support of Excavation (SOE) mid-block
piles in block 1121.
-
Mobilize to Southeast
Gas Station (block 1121, lot 47); Start
drilling SOE piles, install construction
fence on Vanderbilt Avenue, partial
closing of sidewalk will occur in
connection with appropriate DOT permits.
-
Test pile for Temporary
Train Trestle foundation piles.
-
Test pits on Pacific
Street within the area which has already
been closed pursuant to the Pacific
Street Maintenance and Protection of
Traffic Plan (MPT) on block 1121 to
confirm location of existing street
utilities proximate to layout of piles.
-
Grade South Lead Track
for LIRR access to East Portal.
-
Excavation in block 1121
west to east.
-
Test pits under ramp in
block 1121.
Abatement and Demolition Work
All work described below
will comply with the additional oversight
and protocols by the Department of Buildings
(DOB) that were established on April 30th.
-
The double-shift
abatement and emergency demolition work
on the parapets at 800 Pacific Street
will continue for the next four-five
weeks. Once this work is completed,
demolition of the rest of the building
will commence.
-
Demolition of 546
Vanderbilt Avenue (block 1129, lot 54)
will commence, and is anticipated to be
underway for the next two months.
-
Demolition of 622
Atlantic Avenue (block 1119, lot 1) will
be completed within this two week
period.
-
Abatement has been
completed at 175 Flatbush Avenue (block
1118, lot 6), and 177 Flatbush Avenue
(block 1118, lot 5). Demolition will
commence within this two week period.
-
Abatement will commence
at 814 Pacific Street (block 1129, lot
45), 818 Pacific Street (block 1129, lot
46), and 542 Vanderbilt Avenue (block
1129, lot 50).
Utility Work
The sidewalk shed constructed over a transit
manhole in the sidewalk on Flatbush Avenue
between Atlantic Avenue and Pacific Street
will remain in place to prepare the manhole
for cable insulation, abatement and
reconstruction as part of the private
utility/transit relocation work required to
accommodate new sewer infrastructure. This
work will continue through August.
|
|
|
|