Atlantic Yards Arena and
Redevelopment Project
ATLANTIC YARDS CONSTRUCTION
UPDATE
Weeks beginning May 5, 2008 and May 12, 2008
In an effort to keep the Atlantic
Yards Community aware of upcoming construction
activities, ESD and Forest City Ratner provide the
following outline of anticipated upcoming
construction activities.
Please note: the scope and nature of activities are
subject to change based upon field conditions. All
work has been approved by appropriate City and State
agencies where required.
In addition to the activities described below noise
attenuation and vibration monitoring measures are
underway in connection with the Memorandum of
Environmental Commitments dated 12/08/06.
If you have any questions please feel free to
contact our project Ombudsperson at:
212-803-3233 or
AtlanticYards@empire.state.ny.us
Long Island Rail Road/Vanderbilt Yard Work
-
Continue excavation, lagging and
walers at SOE piles in Southeast Gas Station
(block 1121, lot 47).
-
Continue construction and debris
removal from block 1121.
-
Continue hauling soil from block
1121.
-
Trench and install conduit in
block 1120.
-
Continue demolition of southern
portion of Carlton Avenue Bridge.
-
Prepare and begin foundation
piles for cable bridge (in block 1120, parallel
to 6th Avenue Bridge).
Abatement and Demolition Work
All work described below will comply with the
additional oversight and protocols by the Department
of Buildings (DOB) that were established on April
30, 2007.
-
Demolition is underway at 800
Pacific Street (block 1129, lot 25) and will
continue throughout this two week period.
-
Demolition is complete at 626
Pacific Street (block 1127, lot 22); lot cleanup
will continue.
-
Demolition will begin at 642-646
Pacific Street (block 1127, lot 30) within this
two week period.
-
Demolition will begin at 640
Pacific Street (block 1127, lot 29) within this
two week period.
-
Demolition is complete at 645
Dean Street (block 1129, lot 62).
-
Abatement is complete at 195
Flatbush Avenue (block 1127, lot 1); demolition
will begin within this two week period.
-
Demolition will resume at 585
Dean Street (block 1129, lot 81) within this two
week period.
Utility Work
All utility work scheduled to take place in Flatbush
Avenue will only take place at night (between 10PM
and 6AM) as mandated by DOT.
-
The first of three phases of
upgraded water and sewer installations is
underway and is expected to continue through the
end of the year. Work will continue on Dean
Street between Flatbush and Sixth Avenues and on
Sixth between Pacific and Dean Streets. Night
time work began on Flatbush Avenue at Dean
Street and continued north along Flatbush. Work
is underway on a new sewer chamber on Dean
Street near Flatbush during the day.
-
Transit ducts on Flatbush Avenue
between Atlantic Avenue and Dean Street will be
relocated. This work is expected to continue
over the next three months. All work taking
place in the sidewalk will occur during the day.
Pedestrian walkways will be maintained.
|
|