ATLANTIC YARDS CONSTRUCTION
UPDATE
Weeks beginning July 2, 2007 and July 9,
2007
In an effort to keep the Atlantic Yards
Community aware of upcoming construction
activities, ESD and Forest City Ratner are
providing the following outline of
anticipated upcoming construction
activities.
Please note: the scope and nature of
activities are subject to change based upon
field conditions.
Long Island Rail Road/Vanderbilt Yard Work
-
North sidewalk & north
parking lane closed on Pacific Street
between Carlton & Vanderbilt Avenues.
-
Support of Excavation (SOE)
contractor mobilized drill rig(s).
-
Drill SOE mid-block
piles.
-
Install test pile for
temporary train trestle foundation
piles.
-
Test pits in block 1119
to locate LIRR electrical cable.
-
SOE piles at northeast &
southeast portion of block 1121.
-
Foundation piles for
cable bridge in block 1120.
Abatement and Demolition Work All work described below will comply with
the additional oversight and protocols by
the Department of Buildings (DOB) that were
established on April 30th.
-
The installation of
scaffolding and netting on the Pacific
and Dean Street facades at 800 Pacific
Street (block 1129, lot 25) has been
completed. On Monday, July 2, 2007, the
double-shift abatement and emergency
demolition work will begin on the
parapets. This combination of work is
anticipated to last approximately six
weeks.
-
All of the protective
measures requested by the DOB have been
installed, with the exception of 546
Vanderbilt, where the sidewalk bridge
will be erected in this two week period.
-
Preparation for resuming
abatement and demolition activities will
be underway.
|
|
|
|