Weeks beginning February 25, 2008 – March 3,
2008
In an effort to keep the Atlantic
Yards Community aware of upcoming construction
activities, ESD and Forest City Ratner provide the
following outline of anticipated upcoming
construction activities.
Please note: the scope and nature of activities are
subject to change based upon field conditions. All
work has been approved by appropriate City and State
agencies where required.
In addition to the activities described below noise
attenuation and vibration monitoring measures are
underway in connection with the Memorandum of
Environmental Commitments dated 12/08/06.
If you have any questions please feel free to
contact our project Ombudsperson at:
212-803-3233 or
AtlanticYards@empire.state.ny.us
Long Island Rail Road/Vanderbilt Yard Work
-
Excavation, lagging, install
walers and struts at Support of Excavation (SOE)
piles at Southeast Gas Station (block 1121, lot
47).
-
Continue construction and debris
removal from block 1121.
-
Continue hauling soil from block
1121.
-
Drill piles at East Portal.
-
Trench and install conduit in
block 1120.
-
Prep and begin demo of southern
portion of Carlton Avenue Bridge.
Install protection for traffic and
pedestrians on Pacific Street near 6th Avenue in
preparation for the installation of a footing for
the south foundation of the cable bridge.
Abatement and Demolition Work
All work described below will comply with the
additional oversight and protocols by the Department
of Buildings (DOB) that were established on April
30th.
-
Demolition is underway at 800
Pacific Street (block 1129, lot 25) and will
continue throughout this two week period.
-
Demolition is underway at 626
Pacific Street (block 1127, lot 22) and will
continue throughout this two week period.
-
Abatement is complete at 642-646
Pacific Street (block 1127, lot 30). Demolition
will begin within this two week period.
-
Abatement will begin at 640
Pacific Street (block 1127, lot 29) and will
continue throughout this two week period.
-
Abatement is complete at 645 Dean
Street (block 1129, lot 62).
-
Fencing, back fill and clean up
is complete at 546 Vanderbilt Avenue (block
1129, lot 54). Parging of adjacent walls will be
underway throughout this two week period.
Utility Work
All utility work scheduled to take place in Flatbush
Avenue will only take place at night (between 10PM
and 6AM) as mandated by DOT.
-
The first of three phases of
upgraded water and sewer installations is
underway and is expected to continue through the
end of the year. Work will continue on Dean
Street between Flatbush and Sixth Avenues and on
Sixth between Pacific and Dean Streets. Night
time work began on Flatbush Avenue at Dean
Street and will continue north along Flatbush in
the next two weeks. Work will also begin on a
new sewer chamber on Dean Street near Flatbush
during the day.
-
Transit ducts on Flatbush Avenue
between Atlantic Avenue and Dean Street will be
relocated. This work is expected to continue
over the next three months.
Transportation Update
-
The B65 bus stop on Dean Street
at the east side of Flatbush Avenue has been
temporarily relocated further east on Dean
Street between Carlton and 6th Avenues to
accommodate utility work described above.
-
On January 23, 2008, the Carlton
Avenue Bridge, located between Atlantic Avenue
and Pacific Street, was closed. Northbound
traffic is being rerouted either west along
Pacific Street to Sixth Avenue, which has been
restriped as a two way street, or east along
Pacific Street to Vanderbilt Avenue.
|
|