Atlantic Yards Arena and
Redevelopment Project
ATLANTIC YARDS CONSTRUCTION
UPDATE
Weeks of February 11, 2008 - February 18,
2008
In
In an effort to keep the Atlantic
Yards Community aware of upcoming construction
activities, ESD and Forest City Ratner provide the
following outline of anticipated upcoming
construction activities.
Please note: the scope and nature of activities are
subject to change based upon field conditions. All
work has been approved by appropriate City and State
agencies where required.
In addition to the activities described below noise
attenuation and vibration monitoring measures are
underway in connection with the Memorandum of
Environmental Commitments dated 12/08/06.
If you have any questions please feel free to
contact our project Ombudsperson at:
212-803-3233 or
AtlanticYards@empire.state.ny.us
Long Island Rail Road/Vanderbilt Yard Work
Excavation, lagging, install walers and struts at
Support of Excavation (SOE) piles at Southeast Gas
Station (block 1121, lot 47).
Continue construction and debris removal from
block 1121.
Trench and install conduit in block 1120.
Excavate and pour foundations for temporary access
ramp to yard level in block 1120.
Installation of structure for access ramp.
Excavate and pour south foundation for cable
bridge.
Prep and begin demo of southern portion of Carlton
Av Bridge.
Abatement and Demolition Work
All work described below will comply with the
additional oversight and protocols by the Department
of Buildings (DOB) that were established on April
30th.
Demolition will begin at 800 Pacific Street (block
1129, lot 25) within this two week period.
Abatement is underway at 642-646 Pacific Street
(block 1127, lot 30) and will continue throughout
this two week period.
Abatement is underway at 645 Dean Street (block
1129, lot 62) and will continue throughout this two
week period.
Back fill, clean up and fencing is underway at 546
Vanderbilt Avenue (block 1129, lot 54) and will
continue within this two week period.
Demolition is underway at 626 Pacific Street
(block 1127, lot 22) and will continue within this
two week period.
Utility Work
All utility work scheduled to take place in Flatbush
Avenue will only take place at night (between 10PM
and 6AM) as mandated by DOT.
The first of three phases of upgraded water and
sewer installations is underway and is expected to
continue through the end of the year. Work will
continue on Dean Street between Flatbush and Sixth
Avenues and on Sixth between Pacific and Dean
Streets. Night time work began on Flatbush Avenue at
Dean Street and will continue north along Flatbush
in the next two weeks.
Transit ducts on Flatbush Avenue between Atlantic
Avenue and Dean Street will be relocated. This work
is expected to continue over the next three months.
Transportation Update
The B65 bus stop on Dean Street at the east side
of Flatbush Avenue has been temporarily relocated
further east on Dean Street between Carlton and 6th
Avenues to accommodate utility work described above.
On January 23, 2008, the Carlton Avenue Bridge,
located between Atlantic Avenue and Pacific Street,
was closed. Northbound traffic is being rerouted
either west along Pacific Street to Sixth Avenue,
which has been restriped as a two way street, or
east along Pacific Street to Vanderbilt Avenue.
|
|