Atlantic Yards Arena and
Redevelopment Project
ATLANTIC YARDS CONSTRUCTION
UPDATE Weeks beginning January 28,
2008 and February 4, 2008
In an effort to keep the Atlantic Yards
Community aware of upcoming construction
activities, ESD and Forest City Ratner
provide the following outline of anticipated
upcoming construction activities.
Please note: the scope and nature of
activities are subject to change based upon
field conditions. All work has been approved
by appropriate City and State agencies where
required. In addition to the activities
described below noise attenuation and
vibration monitoring measures are underway
in connection with the Memorandum of
Environmental Commitments dated 12/08/06.
If you have any questions please
feel free to contact our project Ombudsperson at:
212-803-3233 or
AtlanticYards@empire.state.ny.us.
Long Island Rail Road/Vanderbilt Yard Work
- Continue drilling SOE piles at Southeast Gas
Station (block 1121, lot 47).
- Excavate soil at Southeast Gas Station
(block 1121/lot 47).
- SOE piles adjacent to East Portal are
completed.
- Drill piles at LIRR East Portal.
- Continue construction and debris removal
from block 1121.
- Pour foundations for temporary access ramp
to yard level in block 1120.
- Trench and install conduit in block 1120
(for future cable installation from cable bridge
in block 1120, parallel to 6th Avenue Bridge).
- Relocate 3 fire hydrants on north side of
Pacific Street, block 1121.
- Begin demolition of southern portion of
Carlton Avenue Bridge.
Abatement and Demolition Work
All work described below will comply with
the additional oversight and protocols by
the
Department of Buildings (DOB) that were
established on April 30th.
- Mobilization for demolition will begin at
800 Pacific Street (block 1129, lot 25) within
this two week period.
- Abatement will be underway at 642-646
Pacific Street (block 1127, lot 30) within this
two week period.
- Abatement is underway at 645 Dean Street
(block 1129, lot 62) and will continue
throughout this two week period.
- Demolition is complete at 546 Vanderbilt
Avenue (block 1129, lot 54). Back fill, clean up
and fencing will take place during this two week
period.
- Abatement is complete at 626 Pacific Street
(block 1127, lot 22). Demolition will be
underway within this two week period.
Utility Work
All utility work scheduled to take place in
Flatbush Avenue will only take place at night
(between 10PM and 6AM) as mandated by DOT.
- The first of three phases of upgraded water
and sewer installations is underway and is
expected to continue through the end of the
year. Work will continue on Dean Street between
Flatbush and Sixth Avenues and on Sixth between
Pacific and Dean Streets. In the next two weeks,
night time work will begin on Flatbush Avenue at
Dean Street and continue north along Flatbush.
- Transit ducts on Flatbush Avenue between
Atlantic Avenue and Dean Street will be
relocated. This work is expected to continue
over the next three months.
Transportation Update
- The B65 bus stop on Dean Street at the east
side of Flatbush Avenue has been temporarily
relocated further east on Dean Street between
Carlton and 6th Avenues to accommodate utility
work described above.
- On January 23, 2008, the Carlton Avenue
Bridge, located between Atlantic Avenue and
Pacific Street, was closed. Northbound traffic
is being rerouted either west along Pacific
Street to Sixth Avenue, which has been restriped
as a two way street, or east along Pacific
Street to Vanderbilt Avenue.
|
|