Atlantic Yards Arena and
Redevelopment Project
ATLANTIC YARDS CONSTRUCTION
UPDATE Weeks beginning December
31, 2007 and January 7, 2007
In an effort to keep the Atlantic Yards
Community aware of upcoming construction
activities, ESD and Forest City Ratner
provide the following outline of anticipated
upcoming construction activities.
Please note: the scope and nature of
activities are subject to change based upon
field conditions. All work has been approved
by appropriate City and State agencies where
required. In addition to the activities
described below noise attenuation and
vibration monitoring measures are underway
in connection with the Memorandum of
Environmental Commitments dated 12/08/06.
If you have any questions please
feel free to contact our project Ombudsperson at:
212-803-3233 or
AtlanticYards@empire.state.ny.us.
Long Island Rail Road/Vanderbilt Yard Work
- Mid-block Support of Excavation (SOE) piles:
testing in progress; installing tie backs.
- Continue drilling SOE piles at Southeast Gas
Station (block 1121, lot 47).
- Excavation and lagging at SOE piles in
Southeast Gas Station (block 1121/lot 47).
- Drilling of SOE piles adjacent to east
portal.
- Continue preparing site for mobilization to
East Portal to drill SOE and foundation piles.
- Continue drilling Temporary Train Trestle
foundation piles in block 1121.
- Prepare placement of concrete in west
abutment foundation of train trestle.
- Continue construction and debris removal
from block 1121.
- Pour foundations for temporary access ramp
to yard level in block 1120.
- Trench and install conduit in block 1120
(for future cable installation from cable bridge
in block 1120, parallel to 6th Avenue Bridge).
Abatement and Demolition Work
All work described below will comply with
the additional oversight and protocols by
the
Department of Buildings (DOB) that were
established on April 30th.
- Demolition is underway at 546 Vanderbilt
Avenue (block 1129, lot 54) and will continue
for the next two–three months.
- Abatement will be underway at 626 Pacific
Street (block 1127, lot 22) during this two week
period.
Utility Work
-
The first of three phases of upgraded water and
sewer installations is underway and is expected
to continue for four to six months. Work started
on Dean Street at Flatbush Avenue, continued
along Dean to 6th Avenue and will proceed along
6th from Dean to Pacific Street.
Transportation Update
- The B65 bus stop on Dean Street at the east
side of Flatbush Avenue has been temporarily
relocated further east on Dean Street between
Carlton and 6th Avenues to accommodate utility
work described above.
- It is expected that early in 2008, the
Carlton Avenue Bridge will be closed. In
accordance with DOT requirements, the public
will be notified two weeks in advance.
|
|