Atlantic Yards Arena and
Redevelopment Project
ATLANTIC YARDS CONSTRUCTION
UPDATE Weeks beginning December 3,
2007 and December 10, 2007
In an effort to keep the Atlantic Yards
Community aware of upcoming construction
activities, ESD and Forest City Ratner
provide the following outline of anticipated
upcoming construction activities.
Please note: the scope and nature of
activities are subject to change based upon
field conditions. All work has been approved
by appropriate City and State agencies where
required. In addition to the activities
described below noise attenuation and
vibration monitoring measures are underway
in connection with the Memorandum of
Environmental Commitments dated 12/08/06.
Long Island Rail Road/Vanderbilt Yard Work
-
Mid-block Support of Excavation
(SOE) piles: testing in progress; installing tie
backs;
-
Continue drilling SOE piles at
Southeast Gas Station (block 1121, lot 47).
-
Continue preparing site for
mobilization to East Portal to drill SOE and
foundation piles.
-
Continue drilling Temporary
Train Trestle foundation piles in block 1121.
-
Continue construction and debris
removal.
-
Removal of DOT light poles on
north side Pacific Street, block 1121, and
install temporary lighting (current location
interferes with future SOE).
Abatement and Demolition Work
All work described below will comply with
the additional oversight and protocols by
the
Department of Buildings (DOB) that were
established on April 30th.
-
Demolition is complete at 465
Dean Street (block 1127, lot 54). Clean up and
back fill will be completed within this 2-week
period.
-
Demolition is complete at 814
Pacific Street (block 1129, lot 45). Clean up
and back fill will be completed within this
2-week period.
-
Demolition is complete at 538
Vanderbilt Avenue (block 1129, lot 46). Clean up
and back fill will be completed within this
2-week period.
-
Demolition is underway at 546
Vanderbilt Avenue (block 1129, lot 54) and will
continue for the next two–three months.
Utility Work
-
The first of three phases of
upgraded water and sewer installations will be
underway in this two week period and is expected
to be underway for four to six months. Work will
start on Dean Street at Flatbush Avenue,
continue along Dean to 6th Avenue and proceed
along 6th from Dean to Pacific Street.
-
The B65 bus stop on Dean Street
at the east side of Flatbush Avenue will be
temporarily relocated within close proximity to
the current bus stop in the near future to
accommodate imminent utility work. Formal
notification prior to the relocation will occur
in accordance with regulations set forth by the
appropriate city agencies.
|
|