ATLANTIC YARDS CONSTRUCTION
UPDATE
Weeks beginning November 19, 2007 and
November 26, 2007
In an effort to keep the Atlantic Yards
Community aware of upcoming construction
activities, ESD and Forest City Ratner
provide the following outline of anticipated
upcoming construction activities.
Please note: the scope and nature of
activities are subject to change based upon
field conditions. All work has been approved
by appropriate City and State agencies where
required. In addition to the activities
described below noise attenuation and
vibration monitoring measures are underway
in connection with the Memorandum of
Environmental Commitments dated 12/08/06.
Long Island Rail Road/Vanderbilt Yard Work
Mid-block Support of Excavation (SOE)
piles: re-testing anchors
Continue drilling SOE piles at Southeast
Gas Station (block 1121, lot 47).
Continue preparing site for mobilization
to East Portal to drill SOE and foundation
piles .
Continue preparing site to drill
foundation piles for cable bridge (adjacent
to 6th Avenue Bridge, north side of block
1120).
Continue drilling Temporary Train Trestle
foundation piles in block 1121.
Continue construction and debris removal.
Removal of DOT light poles on north side
Pacific Street, block 1121, and install
temporary lighting (current location
interferes with future SOE).
Re-configure fence separating yard
construction from LIRR operations at East
Portal.
Abatement and Demolition Work
All work described below will comply with
the additional oversight and protocols by
the
Department of Buildings (DOB) that were
established on April 30th.
Demolition is underway at 465 Dean Street
(block 1127, lot 54) and will be completed
within this 2-week period.
Demolition will be completed at 814
Pacific Street (block 1129, lot 45) when a
remaining portion at the rear is removed in
conjunction with demolition at 538
Vanderbilt Avenue.
Demolition will be underway at 538
Vanderbilt Avenue (block 1129, lot 46)
within this two week period.
Demolition will be underway at 546
Vanderbilt Avenue (block 1129, lot 54)
within this two-week period and continue for
the next twothree months.
Demolition has been completed at 542
Vanderbilt Avenue (block 1129, lot 50).
Cleanup and back fill is underway.
Utility Work
The first of three phases of upgraded
water and sewer installations will be
underway in this two week period and is
expected to be underway for four to six
months.
Work will start on Dean Street at Flatbush
Avenue, continue along Dean to 6th Avenue
and proceed along 6th from Dean to Pacific
Street.