You Are Here::     
 


1-800-STATE-NY
(1-800-782-8369)

Policies and Disclaimers

Get The Free Acrobat Reader

© 2002 Empire State Development,
All Rights Reserved
 


 
Atlantic Yards Arena  
 

Atlantic Yards Arena and
Redevelopment Project


ATLANTIC YARDS CONSTRUCTION UPDATE
Weeks beginning June 18, 2007 and June 25, 2007


In an effort to keep the Atlantic Yards Community aware of upcoming construction activities, ESD and Forest City Ratner are providing the following outline of anticipated upcoming construction activities.
Please note: the scope and nature of activities are subject to change based upon field conditions.

Long Island Rail Road/Vanderbilt Yard Work
• Materials and equipment will be delivered to the LIRR yard on block 1121 (between Carlton and Vanderbilt Avenues) in support of future excavation activities.

• Support of Excavation (SOE) contractor to deliver partial steel order to block 1121.

• SOE contractor to mobilize drill rig(s) to mid-block of block 1121 and east end of yard.


Abatement and Demolition Work
All work described below will comply with the additional oversight and protocols by the Department of Buildings (DOB) that were established on April 30th.

• Clean-up and backfill will be completed in the next two weeks at 189 Flatbush Avenue (block 1127, lot 12), 191 Flatbush Avenue (block 1127, lot 11) and 618 Pacific Street (block 1127, lot 18) and 193 Flatbush Avenue (block 1127, lot 10) where buildings have been demolished.

• All of the protective measures requested by the DOB have been installed.

• The installation of scaffolding on the Pacific and Dean Street facades at 800 Pacific Street (block 1129, lot 25) will be completed. The double-shift abatement and emergency demolition work will begin on the parapets. This combination of work is anticipated to last approximately six weeks.

• Preparation for resuming abatement and demolition activities will be underway.

• Beginning Monday, June 25, 2007, the northern sidewalk and parking lane of Pacific Street between Carlton and Vanderbilt Avenues will be closed. These closures are required to allow for support of excavation activities associated with the LIRR relocation.

• Beginning Monday, June 25, 2007, jersey barriers will be set up as the fencing of the construction area and steel to be used in the SOE will be delivered. Drill rigs will mobilize on the site as well.

• The closures are being carried under the necessary permits, issued by the Department of Transportation on June 13, 2007

 

 

 

 

 

This site is best viewed with I.E. 6.0 and Macromedia Flash 6.0.
 

Designed by: Light & Power Communications, Ltd